Re/Max Field

Edmonton, Alberta, 2020/2021

Owner

Baseball Edmonton Inc.

Consultant

Select Engineering Consultants Ltd.

Project Budget

$1.00 million

Project Scope

  • Removal 0.50ac area of existing synthetic turf, underlay asphalt, and shale subgrade.
  • Construction of 100m new concrete curb at field edge.
  • Fine grading of 0.96ac area, including installation of geotextile.
  • Installation of over 350m of sub-drainage pipe system.
  • Refinish 0.96ac field area, including repairs and erection of guardrails, installation of Sportsedge flexedge rubber curbing, placement of topsoil and sod, and installation of Tufftrack Grass and Gravel Pavers.
  • Removal of existing and installation of new backstop tension netting.

Challenges

  • Custom fittings required for many existing infrastructure, like the removal of existing backstop netting and welding new engineered supports at great heights for the new tension netting.
  • Tight timeline to complete project for June 2021 game day.


Some Love From Re/Max Field

“I have had the opportunity to work with Delta Valley on the renewal of RE/MAX field in Edmonton. The community group leading the work procured  Delta Valley to complete the work and the City of Edmonton has completed renewal work as a part of the project. Delta Valley has been  professional, timely and the quality of work has been top notch and I wouldn’t hesitate to recommend Delta Valley to others for their landscaping  projects.”

Shannon Hall | Project Manager

VIEW ALL PROJECTS